NextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnailNextGen ScrollGallery thumbnail
1
10
11
12
13
14
15
16
3
4
5
6
7
8
9

Project Owner: Clackamas County
Contract type: Design, Build
Project Timeframe: Three Weeks

Special Features:
Abutment system was built using a “stair-stepped” spread footing design to reduce product and save excavation cost while still maintaining the required scour depth. Wing walls were placed at various angles allowing them to follow the natural curvature of the road.

Project Features:
Bridge was 25’ long with a 20’ clear span and 30’ width. Bridge was placed on a 23 degree skew and a dual plane slope. Project location was on a super elevated corner and the bridge was built to match the existing grades.